Constructing the project
The hangar will room Boeing 767-200 ER or two Herculeses C-130. The object is also equipped with large-size drive-in gate - it is 17 m high and 65 m wide. Aircraft maintenance carried out in the hangar includes repairs of, current service, washing, airscrew and engine replacement. In order to facilitate service maintenance, we installed overhead crane travelling on 5 suspended carriages and heated roof. Scope of the investment also included altitude equipment workshop with 16-meter parachute drying tower as well as technical and social area. Moreover, we were responsible for complex furnishing of the object with office, computer and workshop equipment.
The project in figures
- main hall: 114.426 m³
- workshop and office area: 14.268 m³
- engine and airscrew maintenance workshop:
2.979 m³. - main storage house: 3.393 m³
- altitude equipment and parachute drying workshop: 4.435 m³